News

Cambridge Residents Slam Council Proposal to Delay Bike Lane Construction

News

‘Gender-Affirming Slay Fest’: Harvard College QSA Hosts Annual Queer Prom

News

‘Not Being Nerds’: Harvard Students Dance to Tinashe at Yardfest

News

Wrongful Death Trial Against CAMHS Employee Over 2015 Student Suicide To Begin Tuesday

News

Cornel West, Harvard Affiliates Call for University to Divest from ‘Israeli Apartheid’ at Rally

Z:

THE SCHEME TO STOP THE CONSTRUCTION OF A HIGHWAY INTERCHANGE AND ITS CONSEQUENCES

By Melissa Lee, Crimson Staff Writer

InA CITY WHERE POLITICAL UNITY is a rare phenomenon, the fight to stop a massive highway in terchange from being constructed in Cambridge managed to bring the together disparate interests that usually divide the city.

The story of Scheme Z--the 16-lane, 11-story highway project slated for construction in East Cambridge--is the story of a unique and almost unheard-of political coalition.

It is a coalition that appears to have succeeded. Last March a state-appointed committee recommended that Scheme Z be scrapped in favor of a smaller, more expensive plan.

State officials and the Bridge Design Review committee are nearing agreement of a compromise plan that is "better from a Cambridge perspective," according to Cambridge Conservation Commission Chair Elizabeth Epstein, a committee member.

The new proposal--dubbed 8.1D--would move the highway construction project farther away from the Charles River, lower the height of the roadways and reduce the number of highway ramps and loops by 30 percent, Epstein says.

The plan would also cut the number of miles of highway in half and extend subway and commuter rail lines.

But the improvement--which Stanley H. Durlacher, Assistant Secretary of Transportation and Construction says "strikes a fine balance between many interests"--will inflate the price tag of the project by $200 million. The final price tag will top $630 million.

The cost is significantly lower than the $840 million proposal the Bridge Committee offered last fall, which state administrators said would be far too expensive.

Final plans for 8.1D are months from completion, according to Epstein. The committee has yet to address 21 outstanding issues and complaints that were raised after the new proposal of 8.1 D, victory over the state and over Scheme Z.

Scheme Z was part of a plan to depress the elevated Central Artery underground. Under Scheme Z, four bridges over the Charles River would connect the state's newly depressed Artery with Interstate 93.

The Boston business community and state transportation officials, including former Secretary of Transportation Frederick P. Salvucci, plugged Scheme Z and said the plan was the best and most economical way of constructing the interchange.

But Cantabrigians complained that the Artery was being depressed in Boston at the cost of elevating an environmental monstrosity in Cambridge.

Activists argued that air pollution and traffic volume in the city would skyrocket if the project reached completion.

"The state wanted to do it cheap and dirty and they thought they could get away with it," says Debra M. Mc-Manus, co-chair of the Cambridge Citizens for Livable Neighborhoods--one the community groups leading the struggle against Scheme Z.

The opposition to Scheme Z led a lawsuit that pitted the city of Cambridge against the Commonwealth.

City Councillor Alice K. Wolf says the city's lawsuit is not active now but technically remains alive so the city can "always have recourse to go back to the courts in case the state does not do what it promises."

Wolf adds that although the city has not officially endorsed 8.1D, the final draft of the Bridge Design committee's new plan should be approved by the city and the state within the next year.

The Bridge Design Committee was originally formed by outgoing Secretary of Environmental Affairs John P. DeVillars in January 1991 to make Scheme Z more aesthetically pleasing.

The committee went beyond the mandate, scrapping Scheme Z and voting to replace the controversial plan with another proposal to link Interstate 93 and the Central Artery.

To opponents of Scheme Z, this expected settlement signals the beginning of the end--the specter of a colossal elevated highway is no longer a threat.

And many activists are now praising themselves for organizing a unified opposition to stop the interchange.

Says McManus, "Had we not raised hell, they would have built Scheme Z."

Cantabrigians maintain that the smaller bridges of 8.1D (far left) will avoid much of the negative environmental impact of the 16-lane Scheme Z interchange (near left).

Want to keep up with breaking news? Subscribe to our email newsletter.

Tags