Cambridge On Track to Meet Cycling Safety Ordinance Deadline, Despite Ongoing Construction
Cambridge is on track to meet its Nov. 30 deadline to begin construction on 25 miles of protected bike lanes, but several stretches of the network remain unfinished or in the planning stages.
The Cycling Safety Ordinance was first passed in 2019 and amended in 2020 to mandate the construction of 25 miles of separated bike lanes across the city by May 2026. The deadline has fluctuated since, as city councilors punted it to November 2027 and later moved it back to November 2026 after three cyclists died in car crashes in 2024.
The city is on track to meet its Nov. 30 deadline, even though the construction will not be fully completed. The CSO only requires the construction to be started by the end of the month.
The CSO includes more extensive construction projects, which may involve relocating curbs, removing medians, or modifying underground infrastructure and can take years to complete. But it also counts “Quick-Build” bike lanes, which use pavement markings, flexible posts, signage, and signal changes and can typically be installed within weeks or months.
Jackie McLaughlin, a spokesperson for the city’s Department of Transportation, wrote that the city’s “commitment remains to completing a safe, connected bicycle network across Cambridge,” even though some construction is expected to continue beyond November.
“This work requires careful planning, coordination, and attention to detail to ensure improvements are implemented safely and effectively,” she wrote.
Here’s where the remaining projects stand.
Special4
Four sections of major roads — Cambridge, Broadway, Hampshire, and Garden Streets — make up roughly 7.5 miles of the total network, designated the “Special4.”
Hampshire and Garden Streets were both completed with separated bike lanes in 2024. Roughly 2.72 miles of Broadway Street was completed with quick-build and some constructed bike lanes this year.
Get The Crimson in your inbox.
Construction on much of Cambridge Street has yet to be started. Plans for 1.61 miles of the street have been approved, but have yet to break ground, while the middle half-mile stretch is still being planned. The city has completed 0.08 miles of quick-build bike lanes on Columbia Street so far.
MassAve4
Four segments of the CSO network along Massachusetts Ave. were identified as being particularly challenging to install bike lanes due to existing infrastructure — including MBTA’s overhead bus wires and stops.
Significant sections of this network, such as the 0.12 section from Waterhouse Street to Everett Street, were installed before the CSO took effect. However, no additional construction has been completed since the ordinance was passed.
Roughly 2.66 miles are currently under construction, split between two major sections: a 1.23-mile stretch between Dudley and Beech Street and a 0.98-mile section running from Linnean Street to Waterhouse Street.
Part of the ongoing construction also runs through Harvard Square, with about 0.05 miles running from Church to Garden Street and 0.12 miles running from Plympton to Dunster Street. Both projects remain in the planning phase.
The Rest of Mass. Ave.
The rest of Mass. Ave, stretching from Memorial Drive to Alewife Brook Parkway, is also slated for construction — and the majority has been completed, adding 2.97 miles to the city’s total completed bike lane mileage.
Completed stretches from Dudley Street to Alewife Brook Parkway and from Trow Bridge Street to Inman Street make up significant portions of this mileage, spanning 0.91 miles and 0.9 miles respectively. The majority of the Mass. Ave. bike lanes are quick-build lanes that were completed in 2021 and 2022.
Roughly 1.34 miles are currently still under construction, including a 0.59-mile section through Central Square between Inman Street and Douglass Street.
Other Locations
The remaining mileage that does not fall under the other three projects are classified as “Other Locations” — making up the remainder of the 25-mile network.
The city has completed 10.4 miles of bike lanes across these projects, including a significant 1.65 mile stretch between Mason Street and Mt. Auburn Street. Construction is ongoing on an additional 1.35 miles, including a 0.68-mile segment extending from Memorial Drive to Massachusetts Avenue.
Work on 1.13 miles of the network has yet to begin, including a 0.13 mile section of Steel Place, between Alewife Station Access Road and Cambridgepark Drive, and construction is scheduled to begin in spring 2027.
Christopher A. Cassa — a volunteer with advocacy group Cambridge Bike Safety, which pushed for the CSO in 2019 — acknowledged that unforeseen construction challenges have complicated and delayed the completion of some projects.
“We do recognize that the technical implementation of some of these projects has been more challenging,” Cassa said. “So, where those new challenges have arisen, it’s reasonable to see that the city is being prudent in addressing final configuration changes.”
After Nov. 30, the city plans to continue refining design plans, assessing underground infrastructure, and preparing construction contracts. It also aims to complete the first phase of construction on Massachusetts Avenue between Waterhouse and Linnean streets, begin the second phase, and advance designs for the remaining segments extending to Alewife Brook Parkway.